Construction Update #11

January 14th, 2019

Welcome to the eleventh 45 Broad Street Construction Update! Every three weeks, we will send out a "three-week look-ahead" of the planned construction at our site. We hope that these updates help our neighbors and community stay up-to-date on the progress of our work. If you have questions, concerns, or want more information, please feel free to reach out to us at 45broadstreet@gmail.com.

SUMMARY

Over the past three weeks, we’ve been removing excess soil from some areas, and drilling and pouring secants on the northeast and southeast sides of the site. We’ve also continued the waterproofing along 41 and 55 Broad Street, as well as the demolition along the north wall of the site.

WEEKS OF 1/14+ 1/21 + 1/28

Over the next three weeks, we're working on removing excess soil from some areas, drilling and pouring secants on the northwest and southwest   sides of the site. We’re also continuing the waterproofing along 41 and 55 Broad Street.