Construction Update #9

December 3rd, 2018

Welcome to the ninth 45 Broad Street Construction Update! Every three weeks, we will send out a "three-week look-ahead" of the planned construction at our site. We hope that these updates help our neighbors and community stay up-to-date on the progress of our work. If you have questions, concerns, or want more information, please feel free to reach out to us at 45broadstreet@gmail.com.

SUMMARY

Over the last three weeks we've been waterproofing along 41 and 55 Broad Street, removing overburden, and continuing to drill and pour secants on the site.

WEEKS OF 12/3 + 12/10 + 12/17

Over the next three weeks, we're working on removing excess soil from some areas, drilling and pouring secants on the northeast and southeast sides of the site, and adding minipiles in the center of the site. We’re also continuing the waterproofing along 41 and 55 Broad Street, as well as doing demolition along the north wall of the site.